Manor Farm for Agrivert Operations Ltd

agrivert-logo.png
IMG_4078.jpg
Project Overview

The project was to provide additional silage clamp capacity for an existing on-site anaerobic digestion plant. The works also incl the renewal of all underground drainage systems and the construction of a new lagoon.

Scope of Works
  • Site clearance and bulk earthworks

  • Concrete foundations and substructures

  • Installation of proprietary pre-cast concrete silage wall panels

  • Final asphalt surfacing and finishes

PHOTO-2023-09-08-12-31-42 (12).jpg
Technical Highlights
  • 30,000m3 of bulk earthworks

  • 200 lin m of underground drainage pipework & assoc. manholes

  • Construction of a new 30,000m3 capacity lagoon in an adj. field

  • Installation of 425 lin m of 3m high proprietary sloping ‘ARK’ pre-cast concrete silage wall sections, supplied by specialist Silostop Agri Ltd and shipped from Europe

  • Construction of an proprietary concrete drainage channel to rear of wall sections to ensure compliance with current SSAFO requirements

  • Laying of 6,000m2 of specialist ‘silage mix’ asphalt to clamp floors

Key Facts & Figures
  • ​Client â—‹ Agrivert Operations Ltd

  • ​Contact â—‹ Harry Waters

  • Location â—‹ Towcester, Northamptonshire, UK

  • Contract Value â—‹ £

  • Project Duration â—‹ 18 weeks

  • Completion â—‹ September 2024

Outcome

In challenging weather conditions, the project was delivered safely, on time, and within budget, meeting all client and regulatory requirements. The works have resulted in the AD plant now being able to operate at near-capacity.

PHOTO-2023-09-08-12-31-41 (2).jpg
PHOTO-2023-09-08-12-31-42 (3).jpg
PHOTO-2023-09-08-12-31-42 (1).jpg
Logo_-_Orange (1).png
Holmework is Safe Contractor Approved
Holmework Logo

©2025 HOLMEWORK (YORKS) LTD.

bottom of page