Park Farm for the University of Cambridge

Project Overview
The project was to replace the University’s Park Farm aging silage clamps with brand new up-to-date SSAFO compliant silage clamps. These clamps are to support the farm’s on-site anaerobic digestion plant. The works also incl the renewal of all underground drainage systems incl the installation of large effluent tank.
Scope of Works
-
Site clearance and earthworks
-
Demolition & crushing of the old silage clamp walls & foundations
-
Underground drainage and service installations
-
Concrete foundations and substructures
-
Installation of proprietary pre-cast concrete silage wall panels
-
Final asphalt surfacing and finishes

Technical Highlights
-
Installation of a 75,000 litre, 15m x 3m Ø x 5m deep underground Klargester effluent tank
-
300 lin m of underground drainage pipework & assoc. manholes
-
Placement of over 120m³ of reinforced concrete for foundations, slabs, and retaining structures
-
Installation of 175 lin m of 3m high proprietary LA300g ‘Bosch Beton’ pre-cast concrete silage wall sections, supplied by specialist Silostop Agri Ltd and shipped from Europe
-
Construction of an insitu concrete drainage channel to rear of wall sections to ensure compliance with current SSAFO requirements
-
Laying of 1,500m2 of specialist ‘silage mix’ asphalt to clamp floors
Key Facts & Figures
-
​Client ○ The University of Cambridge
-
​Contact ○ Paul Cole/Paul Kelly, University Estates Dept
-
Location â—‹ Madingley, Cambridge, UK
-
Contract Value â—‹ £ tbc
-
Project Duration â—‹ 18 weeks
-
Completion â—‹ October 2025
Outcome
The project was delivered safely, on time, and within budget, meeting all client and regulatory requirements. Our proactive site management and collaborative approach ensured minimal disruption and a high-quality finished product.



