Park Farm for the University of Cambridge

Project Overview
The project was to replace the University’s Park Farm aging silage clamps with brand new up-to-date SSAFO compliant silage clamps. These clamps are to support the farm’s on-site anaerobic digestion plant. The works also incl the renewal of all underground drainage systems incl the installation of large effluent tank.
Scope of Works
-
Site clearance and earthworks
-
Demolition & crushing of the old silage clamp walls & foundations
-
Underground drainage and service installations
-
Concrete foundations and substructures
-
Installation of proprietary pre-cast concrete silage wall panels
-
Final asphalt surfacing and finishes

Technical Highlights
-
Installation of a 75,000 litre, 15m x 3m Ø x 5m deep underground Klargester effluent tank
-
300 lin m of underground drainage pipework & assoc. manholes
-
Placement of over 120m³ of reinforced concrete for foundations, slabs, and retaining structures
-
Installation of 175 lin m of 3m high proprietary LA300g ‘Bosch Beton’ pre-cast concrete silage wall sections, supplied by specialist Silostop Agri Ltd and shipped from Europe
-
Construction of an insitu concrete drainage channel to rear of wall sections to ensure compliance with current SSAFO requirements
-
Laying of 1,500m2 of specialist ‘silage mix’ asphalt to clamp floors
Key Facts & Figures
-
Client ○ The University of Cambridge
-
Contact ○ Paul Cole/Paul Kelly, University Estates Dept
-
Location ○ Madingley, Cambridge, UK
-
Contract Value ○ £ tbc
-
Project Duration ○ 18 weeks
-
Completion ○ October 2025
Outcome
The project was delivered safely, on time, and within budget, meeting all client and regulatory requirements. Our proactive site management and collaborative approach ensured minimal disruption and a high-quality finished product.



